1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 4- m/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason:- To minimise the impact of building emissions on the local air quality. To comply with Policy DC61 of the Core Strategy and Development Control Policies DPD.
4.Prior to commencement of above ground works of the development hereby permitted, written specification of external walls and roof materials to be used in the construction of the building(s) shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of a written specification prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document.
5.Prior to above ground works of the development hereby permitted details shall be submitted to and approved by the Local Planning Authority for a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
6.Prior to the commencement of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development, prevent undue overlooking of adjoining property and ensure that the development accords with the Development Control Policies Development Plan Document Policy DC61.
7.No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
8.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework 2018.
9.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £1,440 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website.
10.The planning obligations recommended in this report have been subject to the statutory tests set out in Regulation 122 of the Community Infrastructure Levy Regulations 2010 and the obligations are considered to have satisfied the following criteria:- (a) Necessary to make the development acceptable in planning terms; (b) Directly related to the development; and (c) Fairly and reasonably related in scale and kind to the development.
11.A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, (as amended), a fee of £116 per request or £34 where the related permission was for extending or altering a dwellinghouse, is needed.
12.Eastern Power Networks PLC is the electricity distribution network operator in the area. The company is the owner / occupier of the electricity substation located within 6m of the proposed works and it is believed that the proposed works are notifiable under the Part Wall etc, Act 1996. The application has to serve notice in accordance with the Party Wall etc. The Applicant should provide details of the proposed works and liaise with the company to ensure that appropriate protective measures and mitigation solutions are agreed in accordance with the Act. The Applicant would need to be responsible for any costs associated with any appropriate measures required. Any Part Wall Notice should be served on UK Power Networks at its registered office: UK Power Networks, Newington House, 237 Southwark Bridge Road, London SE1 6NP. Contact details: Tel. No: 0330 159 1841 Email: ConsentsEnquiries@ukpowernetworks.co.uk
13.Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see: https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx