No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.Low NOx Boiler Condition Where boliers are proposed, these shall be Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with these details and shall thereafter be permanently retained. Reason: To minimise the impact of building emissions on local air quality.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 the outbuilding hereby permitted shall be used only for purposes incidental to the enjoyment of the dwelling house and not for any trade or business nor as living accommodation. Reason:- To restrict the use to one compatible with a residential area.
5.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of any of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
6.The proposed windows on all east and west first floor elevations shall be permanently glazed with obscure glass not less than level 3 on the standard scale of obscurity and shall thereafter be maintained. Reason:- In the interests of privacy.
7.The rooflights inserted on in the south facing roofslope shall be obscure-glazed, and non-opening unless the parts of the window which can be opened are more than 1.7m above the floor of the room in which the window is installed. Reason - In the interest of privacy and to protect the amenity of the adjacent neighbours
8.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.
9.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). The Mayoral CIL levy rate for Havering is £25/m² and is chargeable for each additional square metre of residential gross internal [floor] (GIA). Based upon the information supplied with the application, the CIL payable would be £3750 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil