| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
| 3. | All new external finishes shall be carried out in materials to match those of the existing building to the satisfaction of the Local Planning Authority.
Reason:-
To safeguard the appearance of the premises and the character of the immediate area, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61. |
| 4. | Prior to the first occupation of the development, the area set aside for car parking as depicted on drawing number: MC002 shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter.
Reason:-
To ensure car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority and in the interest of highway safety. |
| 5. | Minor (up to 9 units):
All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings.
Reason: In order to comply with Policy DC7 of the Local Development Framework and Policy 3.8 of the London Plan. |
| 6. | All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency.
Reason: In order to comply with Policy 5.15 of the London Plan. |
| 7. | Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework 2018. |
| 8. | The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council. If the developer requires scaffolding, hoarding or mobile cranes to be used on the highway, a license is required and Streetcare should be contacted on 01708434343 to make the necessary arrangements.
Please note that unauthorised works on the highway is an offence. |
| 9. | Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access as required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on 01708 433751 to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. |
| 10. | The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development.
Please note that unauthorised work on the highway is an offence. |
| 11. | The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence. |
| 12. | The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development.
Please note that unauthorised work on the highway is an offence. |
| 13. | Before occupation of the residential unit hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see:
https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx |
| 14. | A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, (as amended), a fee of £116 per request or £34 where the related permission was for extending or altering a dwellinghouse, is needed. |