No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.Prior to their use written specification and/or samples of any external materials to be used in the construction of the building shall be submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of a written specification prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.
4.Prior to first occupation of the development hereby permitted details of all proposed walls, fences and boundary treatment shall be submitted to and approved in writing by the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development and prevent undue overlooking of adjoining property.
5.Demolition aside, prior to any above ground work the applicant shall submit to the Local Planning Authority for approval, a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development achieves a satisfactory level of landscape quality.
6.Before the dwellings here permitted are first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety.
7.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no extension or enlargement (including additions to roofs) shall be made to the dwellinghouses hereby permitted, or any detached building erected, without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development.
8.Notwithstanding details shown on submitted plans no building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
9.Notwithstanding details shown on submitted plans no building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally.
10.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
11.No works shall take place in relation to any of the development hereby approved until a Demolition Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing the the Local Planning Authority. The Demolition Method Statement shall include details of: a) Dust management control (including reference to the Control of Dust and Emissions During Construction and Demolition Supplementary Planning Guidance (2014 which was issued by the Mayor of London, which deals particularly with the control of dust and emissions, including the use of non-road mobile machinery); b)Measures for minimising the impact of noise and, if appropriate, vibration arising from demolition activities; c)Details of disposal of waste arising from the demolition works including final disposal points. The buring of wate on the site at any time is specifically precluded. And the works shall be carried out in accordance with the approved details Reason:- In the interests of residential amenity and to reduce emissions from the demolition works in accordance with Policy 34 of the Havering Local Plan and Policies D14 and SI 1 of the London Plan.
12.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity.
13.All dwellings hereby permitted where achievable shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with Policy 7 of the Havering Local Plan and Policy D7 of the London Plan.
14.All hard surfaces hereby approved as part of the development (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the application site. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding.
15.Water efficiency - All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy SI 5 of the London Plan..
16.The development hereby approved shall be fitted with Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with these details and shall thereafter be permanently retained. Reason: To minimise the impact of building emissions on local air quality.
17.Prior to the first occupation of the development hereby approved, the residential parking space(s) shall be provided with active vehicle charging facilities for electric or Ultra-Low Emission vehicles. Reason: Provision prior to first occupation of the proposed dwellings hereby permitted will ensure that the development adequately incorporates measures to allow the use of electric vehicles by future occupiers in accordance with Policy T6.1 of the London Plan.
18.No works shall take place in relation to any of the development hereby approved (except works required to secure compliance with this condition) until the following Contaminated Land reports (as applicable) are submitted to and approved in writing by the Local Planning Authority: a) A Phase I (Desktop Study) Report documenting the history of this site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the site ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Risk Management Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. The report will comprise two parts: Part A - Remediation Scheme which will be fully implemented before it is first occupied. Any variation to the scheme shall be agreed in writing to the Local Planning Authority in advance of works being undertaken. The Remediation Scheme is to include consideration and proposals to deal with situations where, during works on site, contamination is encountered which has not previously been identified. Any further contamination shall be fully assessed and an appropriate remediation scheme submitted to the Local Planning Authority for written approval. Part B - Following completion of the remediation works a 'Validation Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason: To protect those engaged in construction and occupation of the development from potential contamination
19.If during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals, then revised contamination proposals shall be submitted to the LPA; and If during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals. For further guidance see the leaflet titled, 'Land Contamination and the Planning Process'. Reason: Insufficient information has been supplied with the application to judge the risk arising from contamination. Submission of an assessment prior to commencement will ensure the safety of the occupants of the development hereby permitted and the public generally.
20.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the planning agent. They involved alterations to dormer windows. The revisions were provided 11/12/24.