| No. | Condition Text |
|---|
| 1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
| 2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
For the avoidance of doubt and to ensure that the development is carried out as approved. |
| 3. | No above ground works shall take place in relation to any of the development hereby approved until samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials.
Reason:-
Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.. |
| 4. | All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays.
Reason:-
To minimise the impact of the development on the surrounding area in the interests of amenity. |
| 5. | Prior to their installation a scheme for any new plant or machinery shall be submitted to the local planning authority to achieve the following standard. Noise levels expressed as the equivalent continuous sound level LAeq (1 hour) when calculated at the boundary with the nearest noise sensitive premises shall not exceed LA90 -10dB and shall be maintained thereafter to the satisfaction of the Local Planning Authority.
Reason: To prevent noise nuisance to adjoining/adjacent properties. |
| 6. | No building shall be occupied or use commenced until details of any external lighting to the building hereby permitted, has been submitted to and agreed in writing by the Local Planning Authority. The lighting shall be provided and operated in strict accordance with the approved scheme.
Reason: In the interests of amenity and to ensure that any external lighting is appropriate to the setting of the development. |
| 7. | The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £20,200 (this figure may go up or down, subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. |
| 8. | Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework. |