No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans, particulars and specifications. Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
3.Before development is commenced, a scheme shall be submitted to and approved in writing by the Local Planning Authority making provision for a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- To protect residential amenity, and in order that the development accords the Development Control Policies Development Plan Document Policy DC61.
4.Prior to the commencement of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority: a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Remediation Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. d) Following completion of measures identified in the approved remediation scheme mentioned in 1(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority. Reason:- To protect those engaged in construction and occupation of the development from potential contamination and in order that the development accords with Development Control Policies Development Plan Document Policy DC53.
5.a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason:- To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination.
6.The proposed development hereby approved shall be constructed in accordance with the materials detailed under Section 7of the application form unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy DC61 of the Development Control Policies Development Plan Document
7.The premises shall not be used for the purposes hereby permitted other than between the hours of 07:00 and 19:00 hours on Mondays to Fridays and 08:00 and 18:00 on Saturdays, and not at all on Sundays, Bank or Public holidays without the prior consent in writing of the Local Planning Authority. Reason:- To enable the Local Planning Authority to retain control in the interests of amenity, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
8.No deliveries shall be taken at or despatched from the site outside the hours of 07:00 and 19:00 hours Mondays to Fridays and 08:00 and 18:00 on Saturdays. Reason: In the interests of residential amenity and to accord with Policy DC61 of the LDF Development Plan Policies DPD.
9.Prior to the first occupation of the development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/KWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason: To minimise the impact of building emissions on local air quality.
10.Prior to the first occupation of the development hereby permitted, provision shall be made for the storage of refuse awaiting collection according to details which shall previously have been agreed in writing by the Local Planning Authority. Reason:- In the interests of amenity of occupiers of the development and also the visual amenity of the development and the locality generally, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
11.Prior to completion of the works hereby permitted, cycle storage of a type and in a location previously submitted to and agreed in writing by the Local Planning Authority shall be provided and permanently retained thereafter. Reason:- In the interests of providing a wide range of facilities for non-motor car residents, in the interests of sustainability.
12.Notwithstanding the provisions of the Town and Country Planning (Use Classes) Order 1987 or the Town and Country Planning (General Permitted Development) Order 1995 the use hereby permitted shall be for purposes falling within Classes B1(b), B1(c) and B8 and shall be used for no other purpose(s) whatsoever unless otherwise agreed in writing by the Local Planning Authority. Reason:- To restrict the use of the premises to one compatible with the surrounding area and to enable the Local Planning Authority to exercise control over any future use not forming part of this application, and that the development accords with the Development Control Policies Development Plan Document Policy DC61.
13.A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, (as amended), a fee of £116 per request or £34 where the related permission was for extending or altering a dwellinghouse, is needed.
14.Statement Required by Article 31 (cc) of the Town and Country Planning (Development Management) Order 2010: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012.