No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.Before the dwelling hereby permitted is first occupied, the car parking provision as shown on drawing nos. PL06 Revision: B & PL15 Revision: C shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter and shall not be used for any other purpose. Reason:- To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety.
3.Notwithstanding the details on the submitted plans, all new external finishes shall be carried out in materials to match those of the existing building(s) to the satisfaction of the Local Planning Authority. Reason:- To safeguard the appearance of the premises and the character of the immediate area.
4.Prior to above ground works, a scheme need to be submitted and approved by the Local Planning Authority for hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development achieves a satisfactory level of landscape quality.
5.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
6.Prior to the first occupation of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to the first occupation of the development hereby approved will protect the visual amenities of the development, prevent undue overlooking of adjoining property.
7.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future.
8.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (as amended), no development shall take place under Class A, B, C, D and E, Part 1, Schedule 2 of the Order unless permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development.
9.Prior to first occupation, the refuse and recycling facilities as shown on drawing nos. PL06 Revision: B & PL11 Revision: B shall be provided in accordance with details provided and permanently retained thereafter. Reason:- To provide sufficient refuse storage and to protect the amenity of occupiers of the development and also the locality generally.
10.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity.
11.All dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with Policy 7 of the Havering Local Plan and Policy D7 of the London Plan.
12.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy SI 5 of the London Plan.
13.All hard surfaces hereby approved as part of the development (including any sub-base) shall be made of porous materials or provision shall be made to direct run-off water from the hard surface to a permeable or porous area or surface within the curtilage of the application site. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding.
14.The development hereby approved shall be fitted with Ultra-Low NOx boilers with maximum NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOx abatement equipment or technology as determined by a specialist to ensure comparable emissions. The installation of the boilers shall be carried out in strict accordance with these details and shall thereafter be permanently retained. Reason: To minimise the impact of building emissions on local air quality.
15.The development hereby approved shall make provision for at least 1 of the parking spaces to be provided with active charging facilities for use by electric or Ultra-Low Emission vehicles. Such provision is to be made prior to the first occupation of the dwelling hereby permitted. Reason: Provision prior to first occupation of the proposed dwelling hereby permitted will ensure that the development adequately incorporates measures to allow the use of electric vehicles by future occupiers in accordance with Policy T6.1 of the London Plan.
16.Informative: The internal layout of dwelling to be designed, as far as practicable, so that in general the more sensitive living areas, in particular bedrooms are located on facades facing away from the noise source. Double-glazing 6mm.12mm.6mm with opening provided with pressure seals in either hardwood or UPVC frames, with acoustically treated trickle ventilators. A ventilation system that will involve ducting air through the houses, with fresh air obtained either through sound insulated air inlets or from inlets on the quieter side of the buildings.
17.Land Ownership Informative The applicant is advised that this planning permission does not give consent for any part of the development including guttering and fascias to encroach onto any land not within the applicant's ownership.
18.Highways Informatives Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
19.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with Mr Durrani (Agent) by phone and e-mail. The revisions involved in respect to the minimum floor to ceiling height being increased from 2.4m to 2.5m and the removal of front canopy across the front of the proposed dwelling. The amendments were subsequently submitted on 16/1/24, 24/1/24 & 28/02/24.
20.The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). The Mayoral CIL levy rate for Havering is £25/m² and is chargeable for each additional square metre of residential gross internal [floor] (GIA). Based upon the information supplied with the application, £2,050 would be payable due to result in a new residential property with 82m² of GIA, however this may be adjusted subject to indexation. The proposal is also liable for Havering Council's CIL. Havering's CIL charging rate for residential is £125m² (Zone A) for each additional square metre of GIA. Based upon the information supplied with the application, £10,250 would be payable, subject to indexation. These charges are levied under s.206 of the Planning Act 2008. CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. You are also advised to visit the planning portal website where you can download the appropriate document templates at http://www.planningportal.gov.uk/planning/applications/howtoapply/whattosubmit/cil
21.Street Naming and Numbering Inforamtive Before occupation of the residential/ commercial unit(s) hereby approved, it is a requirement to have the property/properties officially Street Named and Numbered by our Street Naming and Numbering Team. Official Street Naming and Numbering will ensure that that Council has record of the property/properties so that future occupants can access our services. Registration will also ensure that emergency services, Land Registry and the Royal Mail have accurate address details. Proof of having officially gone through the Street Naming and Numbering process may also be required for the connection of utilities. For further details on how to apply for registration see: https://www.havering.gov.uk/Pages/Services/Street-names-and-numbering.aspx
22.Party Wall Informative This planning permission does not remove the need to obtain any separate consent of the owner of the adjoining property prior to commencing building works on, under, above or immediately adjacent to their property (e.g. foundations or guttering). The Party Wall Etc. Act 1996 contains requirements to serve notice on adjoining owners of property under certain circumstances, and a procedure exists for resolving disputes. This is a matter of civil law between the two parties, and the Local Planning Authority are not involved in such matters. A free guide called "The Party Wall Etc Act 1996: Explanatory Booklet" is available on the website of the Department for Communities and Local Government. https://www.gov.uk/government/publications/the-party-wall-etc-act-1996-revised-explanatory-booklet