The London Borough Of Havering - Home page

No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.All new external finishes shall be carried out in materials to match those of the existing building(s) to the satisfaction of the Local Planning Authority. Reason:- To safeguard the appearance of the premises and the character of the immediate area, and in order that the development accords with the Development Control Policies Development Plan Document Policy DC61.
3.The extension hereby permitted shall be used only for living accommodation as an integral part of the existing dwelling known as 48 Purbeck Road, Hornchurch and shall not be used as a separate unit of residential accommodation at any time. Reason:- The site is within an area where the Local Planning Authority consider that the sub-division of existing properties should not be permitted in the interests of amenity, and that the development accords with Development Control Policies Development Plan Document Policy DC61.
4.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
5.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Development Control Policies Development Plan Document Policy DC61.
6.No works shall take place in relation to any of the development hereby approved until a site investigation is undertaken to assess the level and extent of any landfill gas present, together with an assessment of associated risks. The investigation shall be in accordance with a scheme submitted to and approved in writing by the Local Planning Authority prior to any development commencing. If during development works any contamination should be encountered which was not previously identified in the Site Investigation then works should halt immediately and the Local Planning Authority consulted to agree appropriate further action. Reason:- The development is situated on or within 250 metres of a current or historic landfill site or gravel pit. Insufficient information has been supplied with the application to judge the risk arising from landfill gas. Submission of an assessment prior to commencement will protect those redeveloping this site and any future occupants from potential landfill gas and will ensure that the development accords with the Development Control Policies Development Plan Document Policies DC54 and DC61.
7.No works shall take place in relation to any of the development hereby approved (except works required to secure compliance with this condition) until the following Contaminated Land reports (as applicable) are submitted to and approved in writing by the Local Planning Authority: a) A Phase I (Desktop Study) Report documenting the history of this site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the site ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase III (Risk Management Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. The report will comprise two parts: Part A - Remediation Scheme which will be fully implemented before it is first occupied. Any variation to the scheme shall be agreed in writing to the Local Planning Authority in advance of works being undertaken. The Remediation Scheme is to include consideration and proposals to deal with situations where, during works on site, contamination is encountered which has not previously been identified. Any further contamination shall be fully assessed and an appropriate remediation scheme submitted to the Local Planning Authority for written approval. Part B - Following completion of the remediation works a 'Validation Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. d) If during development works any contamination should be encountered which was not previously identified and is derived from a different source and/or of a different type to those included in the contamination proposals, then revised contamination proposals shall be submitted to the LPA; and e) If during development work, site contaminants are found in areas previously expected to be clean, then their remediation shall be carried out in line with the agreed contamination proposals. For further guidance see the leaflet titled, 'Land Contamination and the Planning Process'. Reason:- Insufficient information has been supplied with the application to judge the risk arising from contamination. Submission of an assessment prior to commencement will ensure the safety of the occupants of the development hereby permitted and the public generally. It will also ensure that the development accords with Development Control Policies Development Plan Document Policies DC54 and DC61.
8.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 2015, Article 3, Schedule 2, Part 2, Class A no gates, walls or enclosures shall be erected, constructed or altered within the site known as No. 48 Purbeck Road, Hornchurch (including the annex) unless permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason: In order that the annex approved remains ancillary to the main dwelling and that the development accords with Policy DC61 of the Development Control Policies Development Plan Document.
9.The garden area shall not be subdivided at any time and nor shall there be any additional pedestrian or vehicular accesses into the site. Reason:- In order that the annex approved remains ancillary to the main dwelling and that the development accords with Policy DC61 of the Development Control Policies Development Plan Document.
10.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with para 186-187 of the National Planning Policy Framework 2012, improvements required to make the proposal acceptable were negotiated with Mr Letten (agent) by e-mail 14/10/16. The revisions involved removal of the flank door and boundary fence sub-dividing the garden of No.48 Purbeck Road and the garden to the rear of the annexe. The amendments were subsequently submitted on 17/10/16.