No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.FACADE Prior to the commencement of the development hereby approved, the samples or a schedule illustrating the types and colour of the materials to be used in the external finishes (bricks/ roof tiles) shall be submitted to and approved in writing by the local planning authority prior to their first use on site. The development shall be implemented in accordance with the approved details. Prior to any bricks being laid, a brick sample panel, showing the brick type(s), brick bond coursing, mortar and pointing technique, shall be provided on site for inspection and agreed in writing by the Local Planning Authority. The works shall be carried out only in accordance with the agreed sample panel details. Before the new roof(s) hereby approved is/are installed, samples or detailed specifications of the new roof tiles/slates, which shall be natural clay non-interlocking pantiles/natural slates/plain clay tiles/rosemary tiles, shall be submitted to and agreed in writing by the Local Planning Authority. The works shall be carried out only in accordance with the agreed materials. WINDOWS & DOORS Prior to their first installation on-site, additional drawings that show details and specification of proposed new windows, doors, rooflights, fascia and cills to be used, in section and elevation at scales between 1:20 and 1:1 as appropriate, shall be submitted to and approved in writing by the local planning authority. Works shall be implemented in accordance with the approved details and shall be permanently maintained as such. All external windows and doors shall be of a timber or aluminium cladding construction only. Details of their colour, design, specification, method of opening, method of fixing and finish, in the form of drawings and sections of no less than 1:20 scale, shall be submitted to and agreed in writing by the Local Planning Authority before the windows and doors hereby approved are installed. The works shall be carried out only in accordance with the agreed window and door details. In relation to the above condition, trickle vents shall not be inserted into the windows/doors hereby granted consent. Before any window or door heads and cills are installed, details of their design, material and construction, in the form of scale drawings and material samples/specifications, shall be submitted to and agreed in writing by the Local Planning Authority. The works shall be carried out only in accordance with the agreed heads and cills details. Reason:- Insufficient information has been supplied with the application to judge the appropriateness of the doors, windows, materials and rainwater goods to be used. Submission of samples prior to commencement will safeguard the appearance of the building and the character of the immediate area.
3.No works to which this consent relates shall commence until an appropriate programme of historic building recording and analysis has been secured with respect to the main structure as the main barn (identified as EX05) in accordance with a written scheme of investigation, to be approved by the planning authority. Reason; In the interest of the value of historical asset.
4.No development shall take place until there has been submitted to and approved, in writing, by the Local Planning Authority a scheme of hard, soft and boundary treatment landscaping works for the site, which shall include any proposed changes in ground levels and also accurately identify spread, girth and species of all existing trees, shrubs and hedgerows in the surrounding area. A specification of soft landscaping, including proposed trees, plants and seed mixes must be included. The specification should be in line with British Standards and include details of planting works such as preparation, implementation, materials (i.e. soils and mulch), any protection measures that will be put in place (i.e rabbit guards) and any management regimes (including watering schedules) to support establishment. This should be accompanied by a schedule, with details of quantity, species and size/type (bare root, container etc). Hard landscape details such as surface materials and boundary treatments must also be included. The landscape scheme shall be implemented in accordance to the approved details, in the next planting season and managed as such thereafter. Reason: In the interest of biodiversity, sustainability, and to ensure that the landscaping is of high design quality and provides satisfactory standards of visual amenity in accordance with Havering Local Plan Policies 7, 27, 29 and 30 and London Plan Policy G5.
5.No development shall take place until there has been submitted to and approved, in writing, by the Local Planning Authority a landscape management plan for a minimum of 5 years. This should include: a. Drawings showing: 1) The extent of the LMP; i.e. only showing the areas to which the LMP applies, areas of private ownership should be excluded b. Written Specification detailing: 1) All operation and procedures for soft landscape areas; inspection, watering, pruning, cutting, mowing, clearance and removal of arisings and litter, removal of temporary items (fencing, guards and stakes) and replacement of failed planting. All boundary conditions, including site boundary fences, defensible edges to properties, and boundaries to private gardens. Full specification of materials, finishes, and fixings. Detailed drawings, plans and sections 1:5 / 1:10 / 1:20. 2) All operations and procedures for hard landscape areas; inspection, sweeping, clearing of accumulated vegetative material and litter, maintaining edges, and painted or finished surfaces. 3) Furniture (Bins, Benches and Signage) 4) All operations and procedures for surface water drainage system; inspection of linear drains and swales, removal of unwanted vegetative material and litter. c. Maintenance task table which explains the maintenance duties across the site in both chronological and systematic order. The Landscape Management Plan shall be implemented in accordance to the approved details, and managed as such thereafter in the next planting season and managed as such thereafter. Reason: To support plant establishment and ensure appropriate management is carried out and to maintain functionality and visual aesthetic and to comply with Havering Local Plan Policy 7, 27, 29 and 30.
6.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
7.Before the development hereby permitted is first commenced, vehicle cleansing facilities to prevent mud being deposited onto the public highway during construction works shall be provided on site in accordance with details to be first submitted to and approved in writing by the Local Planning Authority. The approved facilities shall be retained thereafter and used at relevant entrances to the site throughout the duration of construction works. If mud or other debris originating from the site is deposited in the public highway, all on-site operations shall cease until it has been removed. The submission will provide; a) A plan showing where vehicles will be parked within the site to be inspected for mud and debris and cleaned if required. The plan should show where construction traffic will access and exit the site from the public highway. b) A description of how the parking area will be surfaced, drained and cleaned to prevent mud, debris and muddy water being tracked onto the public highway; c) A description of how vehicles will be checked before leaving the site - this applies to the vehicle wheels, the underside of vehicles, mud flaps and wheel arches. d) A description of how vehicles will be cleaned. e) A description of how dirty/ muddy water be dealt with after being washing off the vehicles. f) A description of any contingency plan to be used in the event of a break-down of the wheel washing arrangements. Reason:- Insufficient information has been supplied with the application in relation to wheel washing facilities. Submission of details prior to commencement will ensure that the facilities provided prevent materials from the site being deposited on the adjoining public highway, in the interests of highway safety and the amenity of the surrounding area.
8.No building shall be occupied or use commenced until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
9.No building shall be occupied or use commenced until refuse and recycling facilities are provided in accordance with details which shall previously have been submitted to and approved in writing by the Local Planning Authority. The refuse and recycling facilities shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to judge how refuse and recycling will be managed on site. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use will protect the amenity of occupiers of the development and also the locality generally.
10.All building operations in connection with the construction of external walls, roof, and foundations; site excavation or other external site works; works involving the use of plant or machinery; the erection of scaffolding; the delivery of materials; the removal of materials and spoil from the site, and the playing of amplified music shall only take place between the hours of 8.00am and 6.00pm Monday to Friday, and between 8.00am and 1.00pm on Saturdays and not at all on Sundays and Bank Holidays/Public Holidays. Reason:- To protect residential amenity.
11.No works shall take place in relation to any of the development hereby approved until a Construction Method Statement to control the adverse impact of the development on the amenity of the public and nearby occupiers is submitted to and approved in writing by the Local Planning Authority. The Construction Method statement shall include details of: a) parking of vehicles of site personnel and visitors; b) storage of plant and materials; c) dust management controls; d) measures for minimising the impact of noise and ,if appropriate, vibration arising from construction activities; e) predicted noise and, if appropriate, vibration levels for construction using methodologies and at points agreed with the Local Planning Authority; f) scheme for monitoring noise and if appropriate, vibration levels using methodologies and at points agreed with the Local Planning Authorities; g) siting and design of temporary buildings; h) scheme for security fencing/hoardings, depicting a readily visible 24-hour contact number for queries or emergencies; i) details of disposal of waste arising from the construction programme, including final disposal points. The burning of waste on the site at any time is specifically precluded. And the development shall be carried out in accordance with the approved scheme and statement. Reason:- Insufficient information has been supplied with the application in relation to the proposed construction methodology. Submission of details prior to commencement will ensure that the method of construction protects residential amenity.
12.1. 1 ARCHAEOLOGICAL INVESTIGATION: No demolition or development shall take place Until a stage 1 written scheme of investigation (WSI) has been submitted to and approved by the local planning authority in writing. For land that is included within the WSI, no demolition or development shall take place other than in accordance with the agreed WSI, and the programme and methodology of site evaluation and the nomination of a competent person(s) or organisation to undertake the agreed works. If heritage assets of archaeological interest are identified by stage 1 then for those parts of the site which have archaeological interest a stage 2 WSI shall be submitted to and approved by the local planning authority in writing. For land that is included within the stage 2 WSI, no demolition/development shall take place other than in accordance with the agreed stage 2 WSI which shall include: A. The statement of significance and research objectives, the programme and methodology of site investigation and recording and the nomination of a competent person(s) or organisation to undertake the agreed works B. Where appropriate, details of a programme for delivering related positive public benefits C. The programme for post-investigation assessment and subsequent analysis, publication & dissemination and deposition of resulting material. This part of the condition shall not be discharged until these elements have been fulfilled in accordance with the programme set out in the stage 2 WSI. Written schemes of investigation will need to be prepared and implemented by a suitably professionally accredited archaeological practice in accordance with Historic England's Guidelines for Archaeological Projects in Greater London. (Please note, this condition is exempt from deemed discharge under schedule 6 of The Town and Country Planning (Development Management Procedure) (England) Order 2015). 2. CONDITION 2 HISTORIC BUILDING RECORDING No demolition or conversion shall take place until the applicant has secured the implementation of a programme of historic building recording and analysis, which considers agricultural heritage, building structure, architectural detail and archaeological evidence. This shall be undertaken in accordance with a written scheme of investigation submitted by the applicant and approved by the local planning authority. Reason Important structural remains are present on the site. Accordingly, the planning authority wishes to secure the provision of historic building recording prior to development, in accordance with Historic England guidance. Informative; This pre-commencement condition is necessary to safeguard the archaeological interest on this site. Approval of the WSI before works begin on site provides clarity on what investigations are required, and their timing in relation to the development programme. If the applicant does not agree to this pre-commencement condition, please let us know their reasons and any alternatives suggested. Without this pre-commencement condition being imposed the application should be refused as it WOUld not comply with NPPF paragraph 205. It is envisage that the archaeological fieldwork would comprise the following: Evaluation An archaeological field evaluation involves exploratory fieldwork to determine if significant remains are present on a site and if so to define their character, extent, quality and preservation. Field evaluation may involve one or more techniques depending on the nature of the site and its archaeological potential. It will normally include excavation of trial trenches. Afield evaluation report will usually be used to inform a planning decision (predetermination evaluation) but can also be required by condition to refine a mitigation strategy after permission has been granted. Stage 1 should comprise archaeological trial trenching (and possibly test pits within the standing buildings) followed by further investigation in stage 2 if necessary. Historic Building Recording Historic building recording is an investigation to establish the character, history, dating, form and development of a historic building or structure which normally takes place as a condition of planning permission before any alteration or demolition takes place. The outcome will be an archive and a report which may be published. You can find more information on archaeology and planning in Greater London on our website. This response relates solely to archaeological considerations. If necessary, Historic England's Development Advice Team should be consulted separately regarding statutory matters.
13.Prior to the commencement of the development, the details of the any hard surface including the access ways, hereby approved as part of the development (including any sub-base) shall be submitted to and approved in writing by the Local Planning Authority. The scheme shall then be implemented in accordance to the approved details and retained as such thereafter, unless otherwise it is agreed in writing by the local planning authority. Reason:- In order to ensure no water run-off from the hard surface which would contribute to risk of flooding.
14.a) Prior to commencement, a full and detailed application for the Secured by Design award scheme shall be submitted to the Local Planning Authority and the Metropolitan Police NE Designing out Crime Office, demonstrating how Secured by Design Certification will be achieved for this scheme. b) Prior to occupation, the development shall achieve a Certificate of Compliance to the relevant Secure by Design Guide(s) submitted to and approved in writing by the Local Planning Authority in conjunction with the Metropolitan Police. The development shall be carried out in accordance with the approved details and thereafter shall be fully retained and maintained as such for the lifetime of the development. Reason: In the interest of creating safer, sustainable communities.
15.a) Prior to the commencement of the development hereby approved, an Air Quality Neutral Assessment shall be submitted to and agreed by the Local Planning Authority. The assessment shall detail; Calculations of the predicted building emissions and comparison against the Building Emission Benchmarks; Calculations of the predicted transport emissions and comparison against the Transport Emission Benchmarks; Mitigation (if required) or contribution to off-setting the development's emissions, taking into account the most up to date Defra's damage costs and relevant guidance on offsetting payments. b) The use hereby permitted shall not commence until all measures identified in the Air Quality Neutral Assessment have been shown to be implemented to the satisfaction of the Local Planning Authority in writing. Reason: To ensure that the development will not lead to further deterioration of existing poor air quality within the designated Air Quality Management Area and to comply with Policy Sl 1 of the London Plan and relevant guidance, as subsequently amended.
16.Prior to the commencement of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority; a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model. b) A Phase Il (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors. c) A Phase Ill (Remediation Strategy) Report if the Phase Il Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation. d) Following completion of measures identified in the approved remediation scheme mentioned in I(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority. Reason: To protect those engaged in construction and occupation of the development from potential contamination.
17.a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved. b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved. Reason: To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination.
18.The development hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with national optional technical standards as required by Policy SI5 of the London Plan.
19.The development hereby approved shall be provided with air source heat pumps, which shall be designed to comply with "MCS Planning Standards for Permitted Development Installations of Wind Turbines and Air Source Heat Pumps on Domestic Premises". The air source heat pumps shall be provided on site prior to first occupation of the dwellings. Reason: In the interests of sustainability and amenity.
20.(a) Prior to the commencement of development, details of ecological enhancement measures and ecological protection measures shall be submitted to and approved in writing by the Council. This shall detail the biodiversity net gain, plans showing the proposed location of ecological enhancement measures, a sensitive lighting scheme, justification for the location and type of enhancement measures by a qualified ecologist, and how the development will support and protect local wildlife and natural habitats. (b) Prior to the occupation of development, photographic evidence and a post-development ecological field survey and impact assessment shall be submitted to and approved by the Local Planning Authority to demonstrate the delivery of the ecological enhancement and protection measures is in accordance with the approved measures and in accordance with CIEEM standards. Development shall accord with the details as approved and retained for the lifetime of the development. Reason: To ensure that the development provides the maximum provision towards the creation of habitats for biodiversity and the mitigation and adaptation of climate change. In accordance with Policies G1, G5, G6, SI1 and SI2 of the London Plan (2021) and Local Plan.
21.Prior to first occupation of the development hereby approved, details of a scheme showing provision for infrastructure for the charging of electric or Ultra-Low Emission vehicles shall be submitted to and approved in writing by the local planning authority. The submitted scheme shall include provision for at least 20 percent to have active charging facilities and 20% passive provision for with respect to the overspill car parking area, and at least 40 percent to have active charging facilities with remainder passive provision limited only to the permanent parking spaces. The development shall be carried out in accordance with the approved scheme which shall be operational prior to the first occupation of each dwelling and thereafter retained. Reason; In the interest of sustainability.
22.Prior to the commencement of development, an Energy Strategy shall be submitted to and approved in writing by the Local Planning Authority. This strategy shall demonstrate how the development will be zero carbon, and shall deliver CO2 reduction as required by the latest London Plan reequipment in comparison with total emissions from a building which complies with Building Regulations 2013 Part L (with SAP2012 / SAP10 carbon factors) by following the Energy Hierarchy of lean, clean and green measures. The strategy shall confirm the level of reduction in emissions, proposed fabric efficiencies, details to reduce thermal bridging, specifications for the ventilation, renewable energy and hot water and space heating strategies (including their output, efficiency and proposed layout). The final agreed energy strategy shall be installed and operation prior to the first occupation of the development. The development shall be carried out strictly in accordance with the details so approved and shall be operated and maintained as such thereafter. Reason: To ensure the development reduces its impact on climate change by reducing carbon emissions on site in compliance with the Energy Hierarchy, and in line with London Plan (2021) Policy SI2.
23.Prior to the commencement of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of any boundary treatment. Submission of this detail prior to commencement will protect the visual amenities of the development and prevent undue overlooking of adjoining property.
24.The proposals should provide a 2.1 by 2.1 metre pedestrian visibility splay on either side of the proposed access, set back to the boundary of the public footway. There should be no obstruction or object higher than 0.6 metres within the visibility splay. Reason:- In the interests of highway safety.
25.Notwithstanding the provisions of the Town and Country Planning (Use Classes) Order 1987 (as amended) the use hereby permitted shall be for the accommodation of the student attending the associated Amana Trust only and shall be used for no other purpose(s) whatsoever including any other use in Class C2 of the Order, nor should be they be used as an independent dwellings, unless otherwise agreed in writing by the Local Planning Authority. Reason:- To restrict the use of the premises to one compatible with the surrounding area and to enable the Local Planning Authority to exercise control over any future use not forming part of this application.
26.Prior to the commencement of the development the details of surface treatment for the access roads shall be submitted and approved in writing by the Local Planning Authority. The access roads shall be completed in accordance with the approved details. Reason:- To endure a satisfactory external appearance.
27.Changes to the public highway (including permanent or temporary access) - Planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted considered and agreed. If new or amended access is required (whether temporary or permanent), there may be a requirement for the diversion or protection of third party utility plant or highway authority assets and it is recommended that early involvement with the relevant statutory undertaker takes place. The applicant must contact Engineering Services on highwaysDSO@havering.gov.uk to discuss the scheme and commence the relevant highway approvals process. Please note that unauthorised work on the highway is an offence. Highway legislation - The developer (including their representatives and contractors) is advised that planning consent does not discharge the requirements of the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works of any nature) required during the construction of the development. Please note that unauthorised work on the highway is an offence. Temporary use of the public highway - The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a licence from the Council. If the developer required scaffolding, hoarding or mobile cranes to be used on the highway, a licence is required and Street Management should be contacted to make the necessary arrangements. Please note that unauthorised use of the highway for construction works is an offence. Surface water management - The developer is advised that surface water from the development in both its temporary and permanent states should not be discharged onto the highway. Failure to prevent such is an offence.
28.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with the architect responsible for the design, landscaping additional detail information and detail, as well as reduction in the number of car parking spaces for the overflow carparks.