No. | Condition Text |
---|
1. | The development to which this permission relates must be commenced not later than three years from the date of this permission.
Reason:-
To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004). |
2. | The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice).
Reason:-
The Local Planning Authority consider it essential that the whole of the development is carried out and that no departure whatsoever is made from the details approved, since the development would not necessarily be acceptable if partly carried out or carried out differently in any degree from the details submitted. Also, in order that the development accords with Development Control Policies Development Plan Document Policy DC61. |
3. | Before the building(s) hereby permitted is first occupied, the area set aside for car parking shall be laid out and surfaced to the satisfaction of the Local Planning Authority and retained permanently thereafter for the accommodation of vehicles visiting the site and shall not be used for any other purpose.
Reason:-
To ensure that car parking accommodation is made permanently available to the standards adopted by the Local Planning Authority in the interest of highway safety, and that the development accords with the Development Control Policies Development Plan Document Policy DC33. |
4. | No part of the development shall be occupied until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority.
Reason:-
In accordance with Section 197 of the Town and Country Planning Act 1990 and to enhance the visual amenities of the development, and that the development accords with the Development Control Policies Development Plan Document Policy DC61 |
5. | Prior to the occupation of any part of the development hereby approved, details of all proposed walls, fences and boundary treatment shall be submitted to, and approved in writing by, the Local Planning Authority. The boundary development shall then be carried out in accordance with the approved details and retained permanently thereafter to the satisfaction of the Local Planning Authority.
Reason:
To protect the visual amenities of the development and to prevent undue overlooking of adjoining properties and in order that the development accords with Policies DC61 and DC63 of the LDF Development Control Policies Development Plan Document. |
6. | Prior to the occupation of any works pursuant to this permission the developer shall submit for the written approval of the Local Planning Authority;
a) A Phase I (Desktop Study) Report documenting the history of the site, its surrounding area and the likelihood of contaminant/s, their type and extent incorporating a Site Conceptual Model.
b) A Phase II (Site Investigation) Report if the Phase I Report confirms the possibility of a significant risk to any sensitive receptors. This is an intrusive site investigation including factors such as chemical testing, quantitative risk assessment and a description of the sites ground conditions. An updated Site Conceptual Model should be included showing all the potential pollutant linkages and an assessment of risk to identified receptors.
c) A Phase III (Remediation Strategy) Report if the Phase II Report confirms the presence of a significant pollutant linkage requiring remediation. A detailed remediation scheme to bring the site to a condition suitable for the intended use by removing unacceptable risks to all receptors must be prepared, and is subject to the approval in writing of the Local Planning Authority. The scheme must include all works to be undertaken, proposed remediation objectives and remediation criteria, timetable of works, site management procedures and procedure for dealing with previously unidentified any contamination. The scheme must ensure that the site will not qualify as contaminated land under Part 2A of the Environmental Protection Act 1990 in relation to the intended use of the land after remediation.
d) Following completion of measures identified in the approved remediation scheme mentioned in 1(c) above, a "Verification Report" that demonstrates the effectiveness of the remediation carried out, any requirement for longer-term monitoring of contaminant linkages, maintenance and arrangements for contingency action, must be produced, and is subject to the approval in writing of the Local Planning Authority.
Reason:-
To protect those engaged in construction and occupation of the development from potential contamination and in order that the development accords with Development Control Policies Development Plan Document Policy DC53. |
7. | a) If, during development, contamination not previously identified is found to be present at the site then no further development (unless otherwise agreed in writing with the local planning authority) shall be carried out until a remediation strategy detailing how this unsuspected contamination shall be dealt with has been submitted to and approved in writing by the local planning authority. The remediation strategy shall be implemented as approved.
b) Following completion of the remediation works as mentioned in (a) above, a 'Verification Report' must be submitted demonstrating that the works have been carried out satisfactorily and remediation targets have been achieved.
Reason:-
To ensure that any previously unidentified contamination found at the site is investigated and satisfactorily addressed in order to protect those engaged in construction and occupation of the development from potential contamination. |
8. | The proposed development is considered to be in accordance with the aims, objectives and provisions of policies CP1, CP2, CP17, DC2, DC3, DC11, DC33, DC35, DC40, DC 51, DC53, DC55, DC61, DC63 and DC72 of the LDF Core Strategy and Development Control Policies Development Plan Document, Policies 3.3, 3.4, 3.5, 3.8, 6.13, 7.4, and 8.3 of the London Plan, the Residential Extensions & Alterations SPD, the Residential Design SPD, the Planning Obligation SPD, and Section 6 and 7 of the National Planning Policy Framework (NPPF). |
9. | A fee is required when submitting details pursuant to the discharge of conditions. In order to comply with the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 2012, which came into force from 22.11.2012, a fee of £97 per request or £28 where the related permission was for extending or altering a dwellinghouse, is needed. |
10. | The proposal involves works which affect the highway and/or its verge. Before commencing such works you must obtain separate consent of the Highway Authority. Please contact the Streetcare on 01708 432563. |
11. | The Applicant is advised that planning approval does not constitute approval for changes to the public highway. Highway Authority approval will only be given after suitable details have been submitted, considered and agreed. Any proposals which involve building over the public highway as managed by the London Borough of Havering, will require a licence and the applicant must contact StreetCare, Traffic & Engineering on 01708 433750 to commence the Submission/ Licence Approval process.
Should this application be granted planning permission, the developer, their representatives and contractors are advised that this does not discharge the requirements under the New Roads and Street Works Act 1991 and the Traffic Management Act 2004. Formal notifications and approval will be needed for any highway works (including temporary works) required during the construction of the development.
The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council. |
12. | With regards to surface water drainage it is the responsibility of the developer to make proper provision for drainage to ground, water courses or a suitable sewer. In respect of surface water it is recommended that the applicant should ensure that storm flows are attenuated or regulated into the receiving public network through on or off site storage. When it is proposed to connect to a combined public sewer, the site drainage should be separate and combined at the final manhole nearest the boundary. Connections are not permitted for the removal of Ground Water. Where the developer proposes to discharge to a public sewer, prior approval from Thames Water Developer Services will be required. They can be contacted on 0845 850 2777. |
13. | The proposal is liable for the Mayor of London Community Infrastructure Levy (CIL). Based upon the information supplied with the application, the CIL payable would be £3,360 (subject to indexation). CIL is payable within 60 days of commencement of development. A Liability Notice will be sent to the applicant (or anyone else who has assumed liability) shortly and you are required to notify the Council of the commencement of the development before works begin. Further details with regard to CIL are available from the Council's website. |
14. | Statement Required by Article 31 (cc) of the Town and Country Planning (Development Management) Order 2010: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraphs 186-187 of the National Planning Policy Framework 2012. |