1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason: To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans, particulars and specifications (as set out on page one of this decision notice). Reason: In the interest of proper planning and for avoidance of doubt.
3.Before any development above ground level takes place, samples of all materials to be used in the external construction of the building(s) are submitted to and approved in writing by the Local Planning Authority and thereafter the development shall be constructed with the approved materials. Reason: Insufficient information has been supplied with the application to judge the appropriateness of the materials to be used. Submission of samples prior to commencement will ensure that the appearance of the proposed development will harmonise with the character of the surrounding area and comply with Policy Policies 26 and 27 of the Local Plan 2021.
4.No development above ground level shall take place until there has been submitted to and approved by the Local Planning Authority a scheme of hard and soft landscaping, which shall include indications of all existing trees and shrubs on the site, and details of any to be retained, together with measures for the protection in the course of development. The submitted scheme is expected to make provision for planting to the front and side boundaries of the site of a height and type that will provide a sufficient privacy screen to the garden areas of the ground floor units within the development. All planting, seeding or turfing comprised within the scheme shall be carried out in the first planting season following completion of the development and any trees or plants which within a period of 5 years from completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of a similar size and species, unless otherwise agreed in writing by the local Planning Authority. Reason: Insufficient information has been supplied with the application to judge the appropriateness of the hard and soft landscaping proposed. Submission of a scheme prior to commencement will ensure that the development accords with Policy 27 of the Local Plan 2021. It will also ensure accordance with Section 197 of the Town and Country Planning Act 1990.
5.No construction works or deliveries into the site shall take place other than between the hours of 08:00 to 18:00 on Monday to Friday and 08:00 to 13:00 hours on Saturdays unless agreed in writing with the Local Planning Authority. No construction works or deliveries shall take place on Sundays, Bank or Public Holidays unless otherwise agreed in writing by the local planning authority. Reason: To protect residential amenity, and in order that the development accords with Policy 34 of the Local Plan 2021.
6.Prior to the first occupation of development, details shall be submitted to and agreed in writing by the Local Planning Authority for the installation of Ultra-Low NOx boilers with NOx Emissions less than 40 mg/kWh. Where any installations do not meet this emissions standard it should not be operated without the fitting of suitable NOX abatement equipment or technology as determine by a specialist to ensure comparable missions. The installation of the boilers shall be carried out in accordance with the agreed details and shall thereafter be permanently retained. Following installation emissions certificates will need to be provided to the Local Planning Authority to verify boiler emissions. Reason: To minimise the impact of building emissions on local air quality.
7.All dwellings hereby approved shall comply with Regulation 36 (2)(b) and Part G2 of the Building Regulations - Water Efficiency. Reason: In order to comply with Policy SI 5 of the London Plan.
8.The dwellings hereby approved shall be constructed to comply with Part M4(2) of the Building Regulations - Accessible and Adaptable Dwellings. Reason: In order to comply with Policy D7 of the London Plan 2021 and Policy 7 of the Local Plan 2021.
9.No demolition or development shall take place until a written scheme of Investigation (WSI) has been submitted to and approved by the Local Planning Authority in writing. For land that is included within the WSI, no demolition or development shall take place other than in accordance with the agreed WSI, which shall include the statement of significance and research objectives, and ; A. The programme and methodology of site investigation and recording and the nomination of a competent person(s) or organisation to undertake the agreed works. B. Where appropriate, details of a programme for delivering related positive public benefits. C. The programme for post-investigation assessment and subsequent analysis, publication and dissemination and deposition of resulting material. This part of the condition shall not be discharged until these elements have been fulfilled in accordance with the programme set out in the WSI. Reason: To safeguard the archaeological interest on this site. Approval of the WSI before works begin on site provides clarity on what investigations are required, and their timing in relation to the development programme.
10.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no window or other opening (other than those shown on the submitted and approved plan,) shall be formed in the flank wall(s) of the building(s) hereby permitted, unless specific permission under the provisions of the Town and Country Planning Act 1990 has first been sought and obtained in writing from the Local Planning Authority. Reason:- In order to ensure a satisfactory development that will not result in any loss of privacy or damage to the environment of neighbouring properties which exist or may be proposed in the future, and in order that the development accords with Policy 7 of the Local Plan 2021.
11.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015, no extension or enlargement (including additions to roofs) shall be made to the dwellinghouse(s) hereby permitted without the express permission in writing of the Local Planning Authority. Reason:- In the interests of amenity and to enable the Local Planning Authority to retain control over future development, and in order that the development accords with Polices 7 and 26 of the Local Plan 2021.
12.The developer is advised that if construction materials are proposed to be kept on the highway during construction works then they will need to apply for a license from the Council. If the developer requires scaffolding, hoarding or mobile cranes to be used on the highway, a license is required and Streetcare should be contacted on 01708434343 to make the necessary arrangements. Please note that unauthorised works on the highway is an offence.
13.Statement Required by Article 35(2) of the Town and Country Planning (Development Management) Order 2015: No significant problems were identified during the consideration of the application, and therefore it has been determined in accordance with paragraph 38 of the National Planning Policy Framework.
14.The proposed development would create a new floor area equivalent to 204 sqm new gross internal floor space. The proposal is therefore liable for Mayoral CIL (MCIL2) and would incur a charge of £5,100 based on the calculation of £25.00 per square metre. In addition the development would be liable for the Havering Community Infrastructure Levy (HCIL) which was adopted on September 1st 2019. In this location it translates to a charge of £125 per sqm of new floor space. This equates to a charge of £25,500 Each would be subject to indexation.