No.Condition Text
1.The development to which this permission relates must be commenced not later than three years from the date of this permission. Reason:- To comply with the requirements of Section 91 of the Town and Country Planning Act 1990 (as amended by Section 51 of the Planning and Compulsory Purchase Act 2004).
2.The development hereby permitted shall not be carried out otherwise than in complete accordance with the approved plans (as set out on page one of this decision notice). Reason:- For the avoidance of doubt and to ensure that the development is carried out as approved.
3.The proposed development hereby approved shall be constructed in accordance with the materials detailed under Section 14 of the application form unless otherwise agreed in writing by the Local Planning Authority. Reason: To ensure that the appearance of the proposed development will harmonise with the character of the surrounding area.
4.All mitigation and enhancement measures and/or works shall be carried out in accordance with the details contained in the Phase 1 Habitat Survey and Management Recommendations (Complete Ecology Ltd, February 2022) and email from Untitled Practice LLP entitled, '1904 Rainham Riverside - Planning Appl P2062.21 This may include the appointment of an appropriately competent person e.g. an ecological clerk of works (ECoW) to provide on-site ecological expertise during construction. The appointed person shall undertake all activities, and works shall be carried out, in accordance with the approved details. Reason:- To conserve and enhance protected and Priority species and allow the LPA to discharge its duties under the Conservation of Habitats and Species Regulations 2017 (as amended), the Wildlife & Countryside Act 1981 as amended and s40 of the NERC Act 2006 (Priority habitats & species) as updated by the Environment Act 2021.
5.No use shall commence until cycle storage is provided in accordance with details previously submitted to and approved in writing by the Local Planning Authority. The cycle storage shall be permanently retained thereafter. Reason:- Insufficient information has been supplied with the application to demonstrate what facilities will be available for cycle parking. Submission of this detail prior to occupation in the case of new building works or prior to the use commencing in the case of changes of use is in the interests of providing a wide range of facilities for non-motor car residents and sustainability.
6.Prior to commencement of the development, a full and detailed application for the Secured by Design award scheme shall be submitted to the Local Planning Authority and the Metropolitan Police NE Designing out Crime Office, demonstrating how Secured by Design security standards (based on Secured by Design principles) will be achieved for this scheme. Once approved in writing by the Local Planning Authority, in consultation with the Metropolitan Police Designing out Crime Officers, the development shall be carried out in accordance with the agreed details Reason:- Insufficient information has been supplied with the application to judge whether the proposals meet Secured by Design standards. Submission of a full and detailed application prior to commencement is in the interest of creating safer, sustainable communities and to reflect policy in the NPPF.
7.Prior to the first use of the development hereby permitted details of the Riparian lifesaving equipment (life buoys to be provided along the riverfront in accordance with a standard recommended in the 1991 Hayes Report into the Inquiry into River Safety, or such other equivalent standard shall be submitted to and approved in writing, by the Local Planning Authority, in consultation with the Port of London Authority. The details approved pursuant to this condition shall be permanently retained to an acceptable standard Reasons:- Insufficient information has been supplied with the application to judge the appropriateness level of lifesaving equipment to a satisfactory level.
8.Prior to commencement of the development, a construction environmental management plan (CEMP: Biodiversity) shall be submitted to and approved in writing by the local planning authority. The CEMP (Biodiversity) shall include the following. a) Risk assessment of potentially damaging construction activities. b) Identification of "biodiversity protection zones". c) Practical measures (both physical measures and sensitive working practices) to avoid or reduce impacts during construction. This may be provided as a set of method statements, which should include, but not be limited to, measures to protect Water Voles, reptiles, amphibians, nesting birds, foraging bats and rare invertebrates. d) The location and timing of sensitive works to avoid harm to biodiversity features. e) The times during construction when specialist ecologists need to be present on site to oversee works. f) Responsible persons and lines of communication. g) The role and responsibilities on site of an ecological clerk of works (ECoW) or similarly competent person. h) Use of protective fences, exclusion barriers and warning signs. i) Containment, control and removal of the Invasive non-native species present on site The approved CEMP shall be adhered to and implemented throughout the construction period strictly in accordance with the approved details, unless otherwise agreed in writing by the local planning authority Reason: To conserve protected and Priority species and allow the LPA to discharge its duties under the Conservation of Habitats and Species Regulations 2017 (as amended), the Wildlife & Countryside Act 1981 (as amended) and s40 of the NERC Act 2006 (Priority habitats & species).
9.Prior to the first use of the development hereby permitted "A Biodiversity Enhancement Strategy for protected and Priority species prepared by a suitably qualified ecologist shall be submitted to and approved in writing by the local planning authority, in advance of the Landscape and Ecological Management Plan. The content of the Biodiversity Enhancement Strategy shall include the following: a) Purpose and conservation objectives for the proposed enhancement measures; b) detailed designs or product descriptions to achieve stated objectives; c) locations, orientations and heights of proposed enhancement measures by appropriate maps and plans (where relevant); d) persons responsible for implementing the enhancement measures; and e) details of initial aftercare and long-term maintenance (where relevant). The works shall be implemented in accordance with the approved details shall be retained in that manner thereafter." Reason:- To enhance protected and Priority species & habitats and allow the LPA to discharge its duties under the NPPF 2021 and s40 of the NERC Act 2006 (Priority habitats & species).
10.Prior to the first use of the development hereby permitted, a Landscape and Ecological Management Plan (LEMP) shall be submitted to, and be approved in writing by, the local planning authority prior to beneficial use of the development. The content of the LEMP shall include the following: a) Description and evaluation of features to be managed. b) Ecological trends and constraints on site that might influence management. c) Aims and objectives of management. d) locations, orientations and heights of proposed enhancement measures by appropriate maps and plans); e) Appropriate management options for achieving aims and objectives. f) Prescriptions for management actions. g) Preparation of a work schedule (including an annual work plan capable of being rolled forward over a five-year period). h) Details of the body or organisation responsible for implementation of the plan. i) Ongoing monitoring and remedial measures. The LEMP shall also include details of the legal and funding mechanism(s) by which the long-term implementation of the plan will be secured by the developer with the management body(ies) responsible for its delivery. The plan shall also set out (where the results from monitoring show that conservation aims and objectives of the LEMP are not being met) how contingencies and/or remedial action will be identified, agreed and implemented so that the development still delivers the fully functioning biodiversity objectives of the originally approved scheme. The approved plan will be implemented in accordance with the approved details." Reason: To allow the LPA to discharge its duties under the Conservation of Habitats and Species Regulations 2017 (as amended), the Wildlife & Countryside Act 1981 (as amended) and s40 of the NERC Act 2006 (Priority habitats & species)
11.Prior to commencement of the development, no development shall take place until there has been submitted to and approved, in writing, by the Local Planning Authority a scheme of hard, soft landscaping works for the site, which shall include any proposed changes in ground levels and also accurately identify spread, girth and species of all existing trees, shrubs and hedgerows in the surrounding area. Reason:- In the interest of accessibility, visual amenity and the character and appearance of the ate and to comply with Havering Local Plan Policy 26 and 27.
12.Statement Required by Article 35 (2) of the Town and Country Planning (Development Management Procedure) (England) Order 2015: In accordance with paragraph 38 of the National Planning Policy Framework, improvements required to make the proposal acceptable were negotiated with Mr Smith (agent) by email. The revisions involved setting back the Riverside Belveder from the river wall and provide additonal information. The amendments were subsequently submitted on 21/02/22.